Edithvale Road, Edithvale


On behalf of the Victorian Government, the Level Crossing Removal Project is overseeing the removal of 75 dangerous and congested level crossings across Melbourne by 2025.

The level crossing at Edithvale Road in Edithvale is planned to be removed by lowering the rail line into a trench and building a new road at the current level.

The boom gates at the Edithvale Road level crossing are down for an average of 42 minutes during the 7:00am to 9:00am weekday peak.

The project was subject to an Environment Effects Statement (EES) process, due to its proximity to the Edithvale-Seaford Wetlands.

In September 2018, the Minister for Planning’s Assessment of the EES for Edithvale and Bonbeach found that the rail-under-road option would not threaten the wetlands.

Therefore, the proposal to lower the rail line into a trench at Edithvale and Bonbeach, to remove the Edithvale Road and Bondi Road level crossings, and build two new stations, will proceed.

The EES process was finalised in December 2018, when the Federal Minister for the Environment gave approval on matters relevant to the Environment Protection and Biodiversity Conservation Act 1999.

While the EES process has been finalised, there is still more work to do before construction can start. This includes further planning and design work and awarding a construction contract.

Work to remove the level crossing at Edithvale is planned to be completed before 2022.



On behalf of the Victorian Government, the Level Crossing Removal Project is overseeing the removal of 75 dangerous and congested level crossings across Melbourne by 2025.

The level crossing at Edithvale Road in Edithvale is planned to be removed by lowering the rail line into a trench and building a new road at the current level.

The boom gates at the Edithvale Road level crossing are down for an average of 42 minutes during the 7:00am to 9:00am weekday peak.

The project was subject to an Environment Effects Statement (EES) process, due to its proximity to the Edithvale-Seaford Wetlands.

In September 2018, the Minister for Planning’s Assessment of the EES for Edithvale and Bonbeach found that the rail-under-road option would not threaten the wetlands.

Therefore, the proposal to lower the rail line into a trench at Edithvale and Bonbeach, to remove the Edithvale Road and Bondi Road level crossings, and build two new stations, will proceed.

The EES process was finalised in December 2018, when the Federal Minister for the Environment gave approval on matters relevant to the Environment Protection and Biodiversity Conservation Act 1999.

While the EES process has been finalised, there is still more work to do before construction can start. This includes further planning and design work and awarding a construction contract.

Work to remove the level crossing at Edithvale is planned to be completed before 2022.


  • Get involved: Edithvale Road, Edithvale

    Thank you to those who came along to our September workshop. You can still be involved and provide your feedback via our short survey on:

    1.  pedestrian rail crossings

    2.  cycling and pedestrian shared use path

    3.  improving the station precinct

    4.  minimising disruption.

    Survey closes Sunday 10 December 2017.

    Thank you to those who came along to our September workshop. You can still be involved and provide your feedback via our short survey on:

    1.  pedestrian rail crossings

    2.  cycling and pedestrian shared use path

    3.  improving the station precinct

    4.  minimising disruption.

    Survey closes Sunday 10 December 2017.
    Take Survey
  • CLOSED: The CRG nominations have concluded.

    CRG Nomination Form

    Nominations are invited from members of the Edithvale and Bonbeach communities who feel passionate about their local area and wish to be involved in the combined Community Reference Group for the Edithvale and Bonbeach level crossing removal projects. 

    Local perspectives and insight are important as we prepare our Environmental Effects Statement and as we look to minimise future construction impacts. 

    If you’re living, learning or working in the area and have an interest in how the project will affect you and your community, we want to hear from you!

    CRG Role

    The purpose of the CRG is to ensure that
    Nominations are invited from members of the Edithvale and Bonbeach communities who feel passionate about their local area and wish to be involved in the combined Community Reference Group for the Edithvale and Bonbeach level crossing removal projects. 

    Local perspectives and insight are important as we prepare our Environmental Effects Statement and as we look to minimise future construction impacts. 

    If you’re living, learning or working in the area and have an interest in how the project will affect you and your community, we want to hear from you!

    CRG Role

    The purpose of the CRG is to ensure that local community
    members can learn more about both the Edithvale and
    Bonbeach level crossing removal projects.

    The CRG will assist the project team by:

    • providing a local perspective, particularly in relation to project design and minimising construction impacts on local communities
    • bringing local knowledge/networks to encourage discussions with interested and affected residents, businesses, interest and industry groups
    • creating opportunities for individuals and groups affected by the project to participate in the projects community events.

    Nominations are due 19 July 2017
    Take Survey
  • CLOSED: This survey has concluded.

    Take our survey

    Welcome to our survey - we're keen to hear from you about level crossing removals in your area. This survey should take about 5-10 minutes to complete. Feel free to skip sections (unless they are marked with an *).

    Thanks for taking the time to provide us with your feedback.

    Level crossing removal option 1

    Lower the rail line into a trench and build a new Edithvale Road bridge at the current road level.

    Key information

    • Depth of rail trench approximately 8 metres
    • Width of rail trench approximately 12 metres
    • Single pedestrian crossing at ground level 
    • Two pedestrian overpasses

    Welcome to our survey - we're keen to hear from you about level crossing removals in your area. This survey should take about 5-10 minutes to complete. Feel free to skip sections (unless they are marked with an *).

    Thanks for taking the time to provide us with your feedback.

    Level crossing removal option 1

    Lower the rail line into a trench and build a new Edithvale Road bridge at the current road level.

    Key information

    • Depth of rail trench approximately 8 metres
    • Width of rail trench approximately 12 metres
    • Single pedestrian crossing at ground level 
    • Two pedestrian overpasses
    • Length of rail trench approximately 1000m

    Level crossing removal option 2

    Raise the rail line over Edithvale Road and retain the existing road level at Edithvale Road and the Nepean Highway.


    Key information

    • Height of rail bridge approximately 8 metres
    • Width of rail bridge approximately 12 metres
    • Length of rail bridge approximately 1000 metres