Hallam Road, Hallam

The dangerous and congested Hallam Road level crossing will be removed by building a rail bridge over Hallam Road and a new modern station.

Extensive site investigations and engineering assessments have found the rail bridge design is the best way to remove the level crossing.

A new elevated station will be built at Hallam, with modern facilities for the 2,200 passengers who use the station each day, and improved pedestrian and cycling connections around the station precinct.

Early works on the Hallam level crossing are expected to start in 2020, with the level crossing to be removed in 2022.

To keep up to date with the progress, please sign up to email updates.

The dangerous and congested Hallam Road level crossing will be removed by building a rail bridge over Hallam Road and a new modern station.

Extensive site investigations and engineering assessments have found the rail bridge design is the best way to remove the level crossing.

A new elevated station will be built at Hallam, with modern facilities for the 2,200 passengers who use the station each day, and improved pedestrian and cycling connections around the station precinct.

Early works on the Hallam level crossing are expected to start in 2020, with the level crossing to be removed in 2022.

To keep up to date with the progress, please sign up to email updates.

  • The Victorian Government has committed to removing the Hallam Road, Hallam level crossing.

    This project will have great community benefits, including making the area safer for pedestrians and cyclists, easing congestion and building a new station.

    Throughout 2019 the Level Crossing Removal Project (LXRP) undertook a range of technical investigations, including

    • traffic data collection
    • feature surveys
    • geotechnical investigations and
    • local utilities assessment.

    Based on these investigations, the project will remove the Hallam Road level crossing by constructing a rail bridge over Hallam Road, including building of a new Hallam Station.

    There

    The Victorian Government has committed to removing the Hallam Road, Hallam level crossing.

    This project will have great community benefits, including making the area safer for pedestrians and cyclists, easing congestion and building a new station.

    Throughout 2019 the Level Crossing Removal Project (LXRP) undertook a range of technical investigations, including

    • traffic data collection
    • feature surveys
    • geotechnical investigations and
    • local utilities assessment.

    Based on these investigations, the project will remove the Hallam Road level crossing by constructing a rail bridge over Hallam Road, including building of a new Hallam Station.

    There are a number of areas of the design that we are seeking community feedback on. Your feedback will help us to understand what is important to the community and what we should consider as we further develop designs.

    A summary of all submissions will be provided to the Minister for Planning as part of a formal request to amend the Casey Planning Scheme.

    Submissions may relate to any aspect of the Hallam Road Level Crossing Removal Project including design considerations, management or mitigation measures for any potential impacts or any other matter relevant to the construction or operation of the project.

    Further information on the design solution will be posted as it becomes available at levelcrossings.vic.gov.au where you can also register for email updates.

    Submissions close 5pm on Friday 6 December 2019.

    Take Survey
  • CLOSED: This survey has concluded.

    The dangerous and congested level crossing at Hallam Road, Hallam is being removed. The crossing will be removed by building a rail bridge over Hallam Road while also delivering a brand new Hallam station. 

    Completing this survey will help us get to know your business and help us plan for construction with as little impact as possible.

    Submissions close 5:00pm Friday 1 November. 

    The dangerous and congested level crossing at Hallam Road, Hallam is being removed. The crossing will be removed by building a rail bridge over Hallam Road while also delivering a brand new Hallam station. 

    Completing this survey will help us get to know your business and help us plan for construction with as little impact as possible.

    Submissions close 5:00pm Friday 1 November. 

    Take Survey
  • CLOSED: This survey has concluded.

    The project team is seeking feedback from the community on what you value about the area and how you move around it. 

    Your feedback will be considered as the project team develops detailed designs.

    Submissions close 5:00pm Friday 1 November. 

    The project team is seeking feedback from the community on what you value about the area and how you move around it. 

    Your feedback will be considered as the project team develops detailed designs.

    Submissions close 5:00pm Friday 1 November. 

    Take Survey